Exclusive: Government and developers privately acknowledged Lanarkshire datacentre site had power provision ‘issue’
-
‘It’s smoke and mirrors’: hope turns to fear in Scottish village chosen for AI datacentre
-
What are Britain’s AI growth zones and are the plans feasible or ‘complete bunk’?
A landmark AI development billed as delivering jobs and prosperity has misrepresented its plans to channel a nuclear reactor’s worth of power to a site in rural Scotland, a Guardian investigation has found.
When it was announced in January, the government promised that an £8.2bn AI datacentre complex in Lanarkshire – built by the US firm CoreWeave and the Scottish company DataVita – would be powered entirely from on-site renewables and built by 2030.